Cheniere’s Corpus Christi is moving ahead with construction of its liquefied natural gas (LNG) export facility in Texas.
According to the latest filing with the Federal Energy Regulatory Commission (FERC), Cheniere has progressed the project’s Stage 1 to 84 percent completion. Stage 1 includes the construction of liquefaction trains 1 and 2, storage tanks A and C, OSBL, west jetty and east jetty civil works.